Test Performance For Air, Water, Structural (Wind load). Wind Zone 4 (Hurricane) - Cycling and Impact
Performed on a C3 3L1R Outswing Aluminum Folding Door System (met all requirements) |
AAMA / WDMA / CSA 101 / I.S.2 / A440-08 • NAFS-08
Air Infiltration: A2
Water Leakage Resistance: DP70 (510 PA) or PG70 • C3 Storm 45, 70, series and C3 H100 series
Wind Load Resistance: DP70 (3360 PA) (Enhanced System) or PG70 • C3 Storm 70 Series
Wind Load Resistance: DP45 (2160 PA) (Standard System) or PG45 • C3 Storm 45 Series
Wind Zone 4 (Hurricane) ASTM (cycling) E1996: DP100 (C3 H100 Series)
Wind Zone 4 (Hurricane) ASTM (impact) E1886: Pass (C3 H100 Series)
|
|
CAN / CGSB 82.1-M89
Air: A2
Water Leakage Resistance: B4 (510 PA)
Wind Load Resistance: C3
|
| Test Performance for Hurricane Test (Official Results) |
Testing was performed from June 3, 2011 to June 17, 2011. Testing was preformed and evaluated to:
ASTM E1886-08 “Standard Test Method for Performance of Exterior Windows, Curtain Walls, Doors, and
Impact Protective Systems Impacted by Missile(s) and exposed to Cyclic Pressure Differentials”
(ASTM E1886) and ASTM E1996-08 “Standard Specification for Performance of Exterior Windows, Curtain
Walls, Doors and Impact Protective Systems Impacted by Windborne Debris in Hurricanes”
(ASTM E1996) as well as to TAS 201 “Impact Test Procedures” and TAS 203 “Criteria for Testing Products
Subject to Cyclic Wind Pressure loading”
| TEST |
CRITERIA |
RESULTS |
| First Test |
Impact Resistance |
Pass (Wind Zone 4 for ASTM |
| First Test |
Wind Load Cycling @ 70 psf Design Load |
Pass |
| Second Test |
Wind Load Cycling @ 100 psf Design Load |
Pass |
|
| Our Official Lineup Of C3 Systems |
| C3 SYSTEM |
TEST RESULT |
GLASS SPEC |
| C3 Storm 45 |
(DP45 Design Pressure & DP70 Water) |
1” I.G. |
| C3 Storm 70 * |
(DP70 Design Pressure & DP70 Water) |
1” I.G. |
| C3 Hurricane 100 * |
DP100 Design Pressure (Non Water). + Impact / Cycle |
9/16” Hurricane Glass (SentryGlas®) |
Please Note: The C3 Storm 70 and C3 Hurricane 100 had the same additional hardware and special frame installation
details applied to each system in order to reach the above test results. Extra hardware included on the test unit (3L1R) were one extra
twinpoint on #2 panel and wrap around shootbolts on the active #4 panel and wrap around shootbolts on #3 panel. Panel numbers
determined from left to right, viewing system from exterior side.
The C3 Storm 45 and C3 Storm 70 Test units were different from the C3 Hurricane 100 Test unit.
All testing done by Intertek.

|
|
|
|
|
|
|
|